What each certificate confirms, who issues it, and why buyers and banks ask for them.

A completion certificate confirms that a building has been built according to the approved plan. An occupancy certificate (OC) confirms that it is fit to be lived in or used, and allows people to move in. Both are issued by the local authority that approved the plan.

Completion certificate

  • Issued after the authority checks that construction matches the sanctioned plan and building rules.
  • The owner or developer applies with the architect's and engineer's certificates.
  • Some authorities combine it with the occupancy certificate.

Occupancy certificate

  • Confirms that the building is safe to occupy, with water, sewerage, electricity and fire-safety arrangements as required.
  • Needed before occupying the building, for utility connections in many cities, and for the property's legal status.

Why buyers and banks ask for them

  • A building without an OC may be treated as unauthorised, and can face penalties or disconnection.
  • Many banks do not lend, or lend less, on property without an OC.
  • Resale and registration are easier with both certificates in place.

If the building differs from the plan

Minor deviations may be regularised for a fee under the local rules; major ones may have to be removed before the certificates are issued. An architect can check the building against the plan and advise.